New NE Tower Now Open

9/26/2019

On September 25, 2019, new elevators and stairwells in the northeast corner of the building opened to the public. New stairs in the southwest corner are also now open, with the adjacent elevators scheduled to open in approximately one month. The old elevator and stair towers will be demolished as part of Phase 2 of the project, and replaced with new ground floor retail spaces.

Garage Access Status

  • The parking garage is open.

  • The Southwest elevator is closed.

  • The Southwest stairwell is open.

  • The Northeast stairwell is open.

  • The Northeast elevator is open.

  • The Southeast tower is closed.

  • The Northwest tower is closed.

The new tower and stairwell is more open and bright than the old tower